Things are really starting to take shape at The Legacy! Over the past two months, construction has made exciting progress as the building continues to rise in the heart of Evanston.
September: Building the Foundation
September was all about laying the groundwork for what’s to come. The excavation work was completed, and concrete crews made significant progress on the building’s foundation, including the foundation walls and structural supports.
By the end of the month, work had advanced to the second floor, with crews beginning to install the framework and reinforcing materials that will support the floors above. Underground electrical work also moved forward, helping prepare the site for future utility connections.
October: Going Up!
October brought even more visible progress as The Legacy continued to grow vertically. The second-floor concrete was completed, followed by major progress on the third floor. Crews also began work on the fourth-floor structure by the end of the month.
One exciting milestone was progress on the future third-floor pool, with its concrete base and walls taking shape! Behind the scenes, electrical, plumbing, and other building systems are being installed alongside the structural work to keep everything moving forward.
And there's more to look forward to! The window panels for Levels 3, 4, and 5 have officially been manufactured and are now making their way from Shanghai to the United States. These panels will be an important part of bringing The Legacy's exterior to life.
What's Next?
With each passing month, The Legacy is becoming more of a reality. As construction continues upward and more building features take shape, we're excited to share the progress along the way.
Stay tuned for more updates as we get closer to creating a new place to call home in Evanston!